Jump to content


  • Tweets

  • Posts

    • @FTMDave  -  Simeon's had a go at incorporating the attachments at #100 (I think?) but I think what he's done needs tidying up.  But as you say that's just an admin/clerical task and all simeon needs to do is to ensure that it all hangs together and makes sense.  Doesn't require specialist knowledge.   I agree with your comment regarding my paras 13 and 14.  You've made it clearer than I did!   I've also advised simeon to incorporate the report he got from the surveyor.  (Was it Hale Survey Limited?)  Let's see how he got on.   Oh - I also introbuced an error in my draft.  I had simeon down as paying the piling company £3300 but it was only £3000 (I think).  Simeon needs to check that the correct figure is in.  (Simeon had corrected my error* in #100.  I think you may have missed that because you've got a day job to do!)   Oh - and of course simeon needs to ensure that he has taken account of the corrections you have made to the claimant/defendant terminology.   Apart from the above and the interest, I'm not sure if anything else is required.  It's up to simeon now...    *I think the only thing simeon changed in #100 from my earlier draft was the piling bill from £3300 to £3000, and he attempted to add the attachments.  It might have been better - and less confusing for you! - if he'd left that until you'd completed your amendments.  Ah well...
    • We don't need the claim form, they are standard so we know what they look like.   We needs (a) the fleecers' particulars of claim verbatim with the amounts they are claiming, and (b) the date of the claim so we know the deadline for getting your defence in.
    • I see simeon  has several quotes for remedial work and also a report on some of the damage.  They need to be given exhibit/attachment numbers and linked to (16) and (17).  That is simple clerical work, you don't need any legal knowledge to do so.   Obviously the piling receipt has to be linked to (10).   As MiE has pointed out, the total needs to go in (18) and personally I would include the four sub-totals in (18 a b c d).  After all, the court did ask for a properly itemised counterclaim.   If simeon can do the above tomorrow we can then add Andyorch's point about interest at the end.
    • Hi, I’m really scared and nervous to write here, as I’ve never done anything like this before.    I had a telephone DWP compliance interview the other week, when I had the letter I thought I’d been called up at random as I couldn’t think what I’d done wrong.  In 2016 I started an open uni course part time as I was working, however a few months later I suddenly became unwell and was off work a year before finally becoming dismissed. I had to claim ESA while I was still employed as I hadn’t paid enough tax. My mum helped me make the ESA claim over the phone and one of the questions was ‘are you in full time education’ which I replied no to, but we said I had as at the OU part time.  I had to attends job centre visits and told them again about my open uni course, and every year I phoned up for a letter to confirm my ESA for my student fee loan and a part time grant.  The compliance officer is investigating me because I hadn’t declared my studying even though he had it down that I said I was with them. So I’ve had to send in all my information on my student grant which is £1155 a year.  I’m terrified of what is going to happen because I’m sure they had everything down about it all. I’m still claiming ESA for my illness and I’m in the support group, and I’m upset because I’m sure everything was down.  I just wondered if anyone knows what’s going to happen to me.    Best wishes 
    • OK, I've sorted out using the correct terminology to refer to the parties.   The original document was absurdly long and filled with waffle. I reduced it. Then MiE did so further – twice. I've continued on the theme and have merged (13) & (14) as I don't think we need to go into detail of why a £2000 payment because £1500, it'd just confuse the judge.  Feel free to disagree!   I've sorted out the new numbering and references to paragraph numbers.   IMO (16) needs beefing up to explain why the builder disappeared, but simeon seems to not want to explain this properly, so so be it.   Apart from that it looks about ready to go.   Counterclaim   1.      The original Claimant agreed to undertake building work (Project 1) at the original Defendant/now Part 20 Counterclaimant’s property in relation to 3 specific areas of work for an agreed price of £4300.  The work was:   a. To underpin the bay window at the property, b. To replace and repair a previously-removed chimney breast and, c. To install a new beam to the patio door.   2.      It was agreed that Project 1 was to be carried out under the instructions of a structural engineer engaged by the Defendant/Part 20 Counterclaimant and that the Claimant’s work would be as a result of instructions received following the structural engineer's assessment of the property.   3.      Between June and July in 2020 the Defendant/Part 20 Counterclaimant provided the Claimant with a full copy of the structural engineer's report which detailed instructions to the Claimant for the works to be carried out.   4.      It was agreed between the parties that the works would commence on 13 August 2020.   5.      It was agreed between the parties that payments for Project 1 would be made in three instalments. The first payment would be made at the start of the Claimant's work. The second payment would be paid at the halfway point of the Claimant's work. The final payment would be made on completion of the total works.   6.      The Claimant commenced work on 13 August 2020 and the first instalment due was paid.     7.      On 24 August 2020 the Claimant asked the Defendant/Part 20 Counterclaimant to arrange an inspection of his work by the Building Control Inspector.  The Claimant also stated that Project 1 was approaching mid-way and the Defendant/Part 20 Counterclaimant paid the second instalment due.   8.      The Building Inspector arrived to inspect the Claimant’s work but the Claimant was absent.  The inspector was obviously very displeased by the standard of the Claimant's work.  The inspector spoke to the Claimant by telephone, asking him why he was absent and interrogating him about the work he had done.  The inspector then gave him some instructions over the telephone and also left a list of instructions with the Defendant/Part 20 Counterclaimant to be passed on to the builder.  The building inspector then said he would be getting in touch with the Defendant/Part 20 Counterclaimant’s structural engineer with his findings and the Defendant/Part 20 Counterclaimant should hear from the engineer soon.   9.      The Defendant/Part 20 Counterclaimant passed on the Building Inspector’s instructions to the Claimant who agreed to follow them.   10.  The structural engineer visited and recommended piling to complete the underpinning for Project 1.  The Claimant explained that he could not undertake this work. The structural engineer then suggested an alternative company to the Defendant/Part 20 Counterclaimant to do the necessary work and this company was engaged by the Defendant/Part 20 Counterclaimant to complete the necessary piling at an additional cost to the Defendant/Part 20 Counterclaimant of £3300. (See receipt at Attachment1).   11.  The Claimant asked if the Defendant/Part 20 Counterclaimant needed any more work to be done and, despite the problems encountered on Project 1, the Defendant/Part 20 Counterclaimant agreed on 7 September 2020 to have more work done (Project 2) at an agreed price of £2580 and on similar payment terms to Project 1.   12.  As work commenced on Project 2 and was continued on the remaining work for Project 1, the Defendant/Part 20 Counterclaimant had occasion to make several complaints to the Claimant regarding the standard of his work.   13.   Barely a week after starting on Project 2, the Claimant demanded payment for that work.  After a period of negotiation the Defendant/Part 20 Counterclaimant paid the Claimant  £1500 in cash.  Both parties agreed that this left a balance outstanding on Project 2 of £1080.   14.  It later came to the Defendant/Part 20 Counterclaimant’s attention that the Claimant had removed material (including a steel beam) from the Defendant/Part 20 Counterclaimant’s property that the Defendant/Part 20 Counterclaimant suspects either belonged to him or had been paid for by him in connection with Project 1.  When challenged the Claimant admitted he had done this.  The Defendant/Part 20 Counterclaimant has included the value of this material in his counterclaim detailed below.   15.    On 21 September 2020 the Defendant/Part 20 Counterclaimant highlighted and sent a snagging list to the Claimant (Attachment 2).  Over a month later the Claimant sent an employee to attend to this work.  It was not carried out satisfactorily and resulted in an updated snagging list being sent to the claimant (Attachment 3).  All of this snagging work remains undone by the Claimant.   16.  Apart from the outstanding snagging work referred to in para 16 above, the Claimant also left other work from Projects 1 and 2 uncompleted.  That work which was not completed is listed at Attachment 4.   17.  During the course of carrying out work on Projects 1 and 2 the Claimant also negligently caused substantial damage to the Defendant/Part 20 Counterclaimant’s property (as itemised in Attachment 5) by not executing the work with the skill expected of a reasonable tradesman.   18.  The Defendant/Part 20 Counterclaimant seeks an order from the court directing the Claimant to pay to the Defendant/Part 20 Counterclaimant the sum of £nnnnnnn {Simeon - put in the actual total amount here) in respect of:   (a)   the cost of the piling referred to in para 10 above which the Claimant could not undertake and another contractor had to be paid to complete; (b)   the cost of completing work the Claimant had left undone from Projects 1 and 2 referred to in para 16 above; (c)   the cost of remedial work to put right the damage negligently caused by the Claimant and referred to in para 17 above; and (d)    the cost of the steel beam referred to in para 14 above.   A receipt in respect of item (a) - see Attachment 1 - and two priced quotes in respect of items (b) and (c) - see Attachments 6 and 7 - are attached in support of this counterclaim.
  • Recommended Topics

  • Our picks

  • Recommended Topics

Notice of intention to file a default from Talk Talk


Recommended Posts

Hi re the above,

since letting my contract lapse in 2020 i continued using Talk Talk internet, at their original monthly cost, until i found a more reliable and cost effective supplier

 

. In February 2021 Talk Talk released details of their proposed price increase and gave me the only option to contact them by phone in order to cease using their broadband to avoid the new tariff!

 

I immediately contacted them advising i was now about to transfer to an alternative supplier and reminded Talk Talk that my contract was lapsed. The customer services confirmed this and stated they would waive the usual termination fees.

 

I received the means to facilitate the return of the usual router etc which i promptly returned on 30.4.21, i have the receipt as proof

 

. I have recently been receiving electronic monthly bills which i  have just ignored, however, this latest letter received today curiously mentions the single amount of £34.18 as an outstanding balance!

 

I do hope all this is clear to understand i look forward to your comments?

Kind regards Madman70

Edited by dx100uk
added A few blank lines only..dx
Link to post
Share on other sites

Send them a subject access request straightaway.

Let us know what you get.

Also, please can you space at your posts rather more. It's very difficult for people with a small screen to follow blocks of text

Link to post
Share on other sites

Post spaced.

 

why dont you scan you proof of posting and send that to them?

 

Dx

please don't hit Quote...just type we know what we said earlier..

DCA's view debtors as suckers, marks and mugs

NO DCA has ANY legal powers whatsoever on ANY debt no matter what it's Type

and they

are NOT and can NEVER  be BAILIFFS. even if a debt has been to court..

If everyone stopped blindly paying DCA's Tomorrow, their industry would collapse overnight... 

Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
 Share

  • Recently Browsing   0 Caggers

    • No registered users viewing this page.

  • Have we helped you ...?


×
×
  • Create New...