Jump to content


  • Tweets

  • Posts

    • I have received a PCN from Euro Car Parks for MFG - Esso Cobham - Gravesend. I was completely unaware that there was any such limit for parking and always considered this to be a service station. I stopped there to use the toilet, have a coffee and made a couple of work calls. I have read the previous topics on this location which suggest I can ignore this and ECP will not take legal action. The one possible complication is that the vehicle is leased by my employer so I do not want to involve them with the associated reminders and threatening letters. The PCN was first issued to the leasing company Arval who have notified ECP of the hiring company. I have attached a copy of the PCN Notice to Hirer with details removed as per instructions. What options do I have or should I just pay the PCN promptly at the reduced rate of £60? img20240424_23142631.pdf
    • What you have uploaded is a letter with daft empty threats from third-party paper tigers.  Just ignore it. What we need to see is the original invoice you received last October or November.
    • Thanks for posting the CPR contents. i do wish you hadn't blanked out the dates and times since at times they can be relevant . Can you please repost including times and dates. They say that they sent a copy of  the original  PCN that they sent to the Hirer  along with your hire agreement documents. Did you receive them and if so can you please upload the original PCN without erasing dates and times. If they did include  all the paperwork they said, then that PCN is pretty near compliant except for their error with the discount time. In the Act it isn't actually specified but to offer a discount for 14 days from the OFFENCE is a joke. the offence occurred probably a couple of months prior to you receiving your Notice to Hirer.  Also the words in parentheses n the Act have been missed off. Section 14 [5][c] (c)warn the hirer that if, after the period of 21 days beginning with the day after that on which the notice to hirer is given, the amount of unpaid parking charges referred to in the notice to keeper under paragraph 8(2)(f) or 9(2)(f) (as the case may be) has not been paid in full, the creditor will (if any applicable requirements are met) have the right to recover from the hirer so much of that amount as remains unpaid; Though it states "if any applicable ...." as opposed to "if all applicable......" in Section 8 or 9. Maybe the Site could explain what the difference between the two terms mean if there is a difference. Also on your claim form they keeper referring to you as the driver or the keeper.  You are the Hirer and only the Hirer is responsible for the charge EVEN IF THEY WEREN'T THE DRIVER. So they cannot pursue the driver and nowhere in the Hirer section of the Act is the hirer ever named as the keeper so NPC are pursuing the wrong person.  
  • Recommended Topics

  • Our picks

    • If you are buying a used car – you need to read this survival guide.
      • 1 reply
    • Hello,

      On 15/1/24 booked appointment with Big Motoring World (BMW) to view a mini on 17/1/24 at 8pm at their Enfield dealership.  

      Car was dirty and test drive was two circuits of roundabout on entry to the showroom.  Was p/x my car and rushed by sales exec and a manager into buying the mini and a 3yr warranty that night, sale all wrapped up by 10pm.  They strongly advised me taking warranty out on car that age (2017) and confirmed it was honoured at over 500 UK registered garages.

      The next day, 18/1/24 noticed amber engine warning light on dashboard , immediately phoned BMW aftercare team to ask for it to be investigated asap at nearest garage to me. After 15 mins on hold was told only their 5 service centres across the UK can deal with car issues with earliest date for inspection in March ! Said I’m not happy with that given what sales team advised or driving car. Told an amber warning light only advisory so to drive with caution and call back when light goes red.

      I’m not happy to do this, drive the car or with the after care experience (a sign of further stresses to come) so want a refund and to return the car asap.

      Please can you advise what I need to do today to get this done. 
       

      Many thanks 
      • 81 replies
    • Housing Association property flooding. https://www.consumeractiongroup.co.uk/topic/438641-housing-association-property-flooding/&do=findComment&comment=5124299
      • 161 replies
    • We have finally managed to obtain the transcript of this case.

      The judge's reasoning is very useful and will certainly be helpful in any other cases relating to third-party rights where the customer has contracted with the courier company by using a broker.
      This is generally speaking the problem with using PackLink who are domiciled in Spain and very conveniently out of reach of the British justice system.

      Frankly I don't think that is any accident.

      One of the points that the judge made was that the customers contract with the broker specifically refers to the courier – and it is clear that the courier knows that they are acting for a third party. There is no need to name the third party. They just have to be recognisably part of a class of person – such as a sender or a recipient of the parcel.

      Please note that a recent case against UPS failed on exactly the same issue with the judge held that the Contracts (Rights of Third Parties) Act 1999 did not apply.

      We will be getting that transcript very soon. We will look at it and we will understand how the judge made such catastrophic mistakes. It was a very poor judgement.
      We will be recommending that people do include this adverse judgement in their bundle so that when they go to county court the judge will see both sides and see the arguments against this adverse judgement.
      Also, we will be to demonstrate to the judge that we are fair-minded and that we don't mind bringing everything to the attention of the judge even if it is against our own interests.
      This is good ethical practice.

      It would be very nice if the parcel delivery companies – including EVRi – practised this kind of thing as well.

       

      OT APPROVED, 365MC637, FAROOQ, EVRi, 12.07.23 (BRENT) - J v4.pdf
        • Like
  • Recommended Topics

Builder not completing snagging issues


style="text-align: center;">  

Thread Locked

because no one has posted on it for the last 4280 days.

If you need to add something to this thread then

 

Please click the "Report " link

 

at the bottom of one of the posts.

 

If you want to post a new story then

Please

Start your own new thread

That way you will attract more attention to your story and get more visitors and more help 

 

Thanks

Recommended Posts

Hi Guys,

 

Looking for some advice regarding snagging, certificates & BC at the end of a building project.

 

The majority of the works were completed in Feb (3 months late), the builder is now ignoring our letters, calls and emails requesting their return to complete the snagging list.

 

We're holding a retainer for the snagging which should just cover the outstanding work but any certificates & warranties are all held by the builder.

 

We would like to get a new builder in to finish the snagging but are worried that we would then struggle to get final sign of by building control and would have no warranties for things like windows & boilers.

 

Can anyone offer any advice? We have tried every option of solving this amicably with the builder but I guess they have now decided the cost to them of rectifying the problems is greater than we owe.

 

Thanks,

Link to post
Share on other sites

I don't know much about building contral but surely it is ossed by your local authrority - in which case you should write to them and complain - ask for another inspection and for a duplicate certificate to be issued to you. Maybe this isn't possible.

 

Additionally I would sue the builder for the delay and for the breach. I wouldn't waste any time. 7 day LBA and let him know that he will be named on a major internet forum if you have to go to court and you get judgment.

 

Frankly I don't see any point in not doing this and I don't see any point in hanging around.

Edited by Conniff
typo
Link to post
Share on other sites

BC certificates are issued for address where the work is carried out so you can ask for a copy of any issued.

if none have been issued then the planning guys will come out and inspect and issue certificates on the build or advise what needs doing to complete.

Give planning a call as they are usually very helpful and respond fairly speedily.

 

Certificates for windows can be obtained on line from fensa. http://www.fensa.co.uk/asp/certificate.asp

 

As for the builder, see Bankfodder's comments.

Link to post
Share on other sites

BC certificates are issued to the employer after the final inspection and if everything is satisfactory, so you should have no worries, but speak to Building Control.

What sort of Contract did you have the Buider?

RIBA home owners contract or similar? There are clauses dealing with non-performance procedures etc.

Link to post
Share on other sites

  • 1 month later...

1. Call your local Building control and ask them to come around for a site visit. They are much obliged to help you out and are there to support the build to progress. In this meeting tell them about your situation with your builder. Ask what they need for the final inspection and how they can support you to get those things in order. In some cases you might find that building Regs might even speak to the builder as they usually are only a few of them dealing with the same builders all the time.

 

Building control will need the following certificates:

1. Electrical Installation : If your builder has done the electrical certification > in other words went around the house and tested all sockets, cales and fuses than he is by law required to file for a electrical installation certificate of compliance with the EIC. ( I understand that this needs to be done within a month or 2 of inspection).

If he has done it a confirmation will be automatically send to you the occupier/homeowner. > This confirmation is all Building Regs requires.

If he has not done it he is in breach of NICEIC rules which you should discuss with your building regs officer and inform the NICEIC.

Solution than is to have building regs arrange for an electric inspection. Not easy and liked but can be done.

 

2. Gas safe certification

The same applies as above with the difference that the regulating body is the Gas safe register.

Once your propoerty is checked and registered you will automatically receive a gas safe certificate from the Gas safe organisation. If you have not received it chances are that your property either has not been inspected or the builder has not registered the inspection. Both are mandatory and again should be discussed with your building regs officer as you will need to have it reinspected.

 

3. Hetas - If you have an open fire. ( Don't know about the process)

4. WAT: This is a questionaire you fill out with your code assesment which highlights the water consumption of the house and that it is in accordance with the applicable code standard. Building regs will test the water flow in the final inspection.

5. Windows or other warranties: I would go to the supplier/ manufacturer and request for them to send you a copy of the warranty directly.

My understanding is that Building regs won't request these - they can advice.

 

Building regs will re-insept all stages during final inspection and can if the certificates are in order sign the completion certificate which you need for your warranty provider. No need for your builder.

 

While you solve your problem and progress with your home you should cover your bases and always stay communicative to the builder. IN WRITING - recorded signed for.

 

After talking to building regs write a consolidated letter to your builders listing the timelines of requests for snagging and the request for warrantys and certificates.

Re-iterate your requests and give 14 days notice to supply and start the snagging process.

If your builder does not adhere to the process I would personally write a letter informing that you will undertake the organisation of snagging jobs to be completed yourself and the retainer will be used to correct their shortfall. Go ahead and get the jobs finished.

Once completed list the final sums of invoices against the retainer. close the contract.

 

If this is more than the retainer invoice him for the overspend. > ittle to no chance you will get it but you are doing the correct thing.

 

You can of course get legal advice and try to go to mediation process or / and court but that will cost you time and money and most likely won't resolve your issues.

 

Good Luck!

Link to post