Jump to content

dukewood

Registered Users

Change your profile picture
  • Posts

    4
  • Joined

  • Last visited

Posts posted by dukewood

  1. thanks - replies below.

    Can you give some background to the issues ?

    had a leak from a sink causing water damage to ceiling below. fixed the leak. ins co agreed to replace strip of ceiling and redecorate ceiling and room.

     

    As part of the process insurance company sent round the assessor – at that point the assessor saw damage ceiling (with possible have given way due to water) and water staining around the region incident. Photos were taken and it was clear that at that point there was no more water leaking.

     

    The tradesmen were arrived and the proposed work schedule was:

     

     

    • Remove 1200 mm strip of ceiling across the room
    • Replace with new plasterboard
    • Re plaster the entire ceiling
    • wait a few days the plaster to dry out

     

    • redecorate the new ceiling and walls

     

     

    What does it relate to ? -

     

    The job started and the ceiling was removed, replaced and re plastered. the tradesmen didn't fully cleanup is intended to come back a few days later to finish the job after receiving a dried out.

     

    After a couple of days most of the ceiling had dried out however a small stripapproximately 100 mm times 1200 mm located approximately 3/4 of a metre away from the original damage remained wet. I notified insurance company on noticing this and we agreed I would weight over the weekend to see if it's dried out.. What actually happened was that the strip was dry out and then reappear shortly after the shower was used. I notified insurance company who sent the home serve area manager to inspect. He stated the issuewas due to wear and tear to shower sill.

    I thought this was unlikely as it had been no previous problems with the shower and the seal and had been recently replaced. THe .insurance company remains committed to this position.

     

     

    How long ago ? - original incident about3 yrs ago

     

    What communications were made between you and the other side to try to resolve pre the Omb taking it up ?

     

    Following the area managers visit I called them and wrote several occasions. I also included a letter from the builder stating that the balance of probability was that removing the ceiling below and then replacing it could have sufficiently disturbed the shower tray above to cause a leak. It should also be noted that when the tradesmen started work and when the initial inspection was done there was no water in this area.The insurance company were unmoved - soin an effort are move things on I agreed to replace the shower seal to resolve the problem – allow the rest of the work to be done in the room below. In summary shower seal was replaced on at least three occasions but the problem remained. The water below was eventually stopped by builderputting in thick plastic moulding around shower tray. My understanding from several builders is the trays suit the wall or underneath before the tiling and final scene is applied and it is likely that it was this speed of sealant that was cracked/ disturbed by the work below– hence original attempts to replace the sealant didn't work.

     

    I reassessed to insurance company that in my viewit was clear that the new water leak below was caused as a result of the words replace the ceiling. Some 18 months later they offer was to remove the shower and if they found a defect in their work replace everything –and if they didn'tthe cost and management of replacement would be down to me. I think it's clear that this was a completely nonsensical suggestion and also demonstrates a complete lack of understanding the issue/the way shower is installed.

     

     

    What did you supply in evidence to the Omb ?

     

    I sent the ombudsman all the correspondence with insurance company,a letter from the builder and the leaflet showing shower installed on a wooden floor. timbers and found the balance of probability was that because a new physical barrier did stop the leak it was a failure in the sealant due to wear and tear causing the new water below.

    ––

    I believe this proves completely the opposite - ie: there was clearly no water here on inspection prior to the ceiling work and would the tradesman have replaced ceiling if there had been any evidence of water when they removed the new ceiling. Finally replacing the existing sealant three times didn't work suggesting a different problem i.e. a sealant below the tile line between the train the wall had been disturbed as a consequence of movement caused by replacing the ceiling

     

    What did the other side provide ?

     

    How much is involved ?

     

    It's hard to put a value on this as much of it is down to the time I have had to spend joint project managing this:

     

    My estimates would be:

     

    3 @ one days labour (£200) - replacing soon three times - £600

    1 @ labour ( £200) - fitting physical barrier - £800

    sealants * 4 - £48

    plastic barrier - £18

    cleaning up after plaster work ( not done by builders) - £200

     

    waiting 18months - 2 years to resolve and get the decoration eventually done – as the ad says says priceless!

     

    thanks again

  2. Thank you.

     

    Think I will have a try - challenge in my case is that it turns on balance of probability - ie: was it likely / not likely that a shower seal failed due to workman taking down / replacing a section of ceiling directly below.

     

    Builder - says yes - lilkely it was caused by work below -

    Ins Co say no - wear and tear - but how likely is that a seal would fail at exactly the same time as work below?

     

    Any thoughts on presenting the case welcome. Would I need to go to the expense of an independanct surveryor report for the court?

     

    Thanks

  3. Hello

     

    Recently had a decision go against me from the Insurance Ombudsman. Feel really strongly that they haven't understood and that on the balance of probability on the facts I think the company are in the wrong. Does anyway have any experience and / or thoughts re: small claims actions following an ombudsman decision ie:

     

    does the judge look at the facts objectvely or merely side with the company and support the ombudsman's decision.

     

    Any comments welcome.

     

    Many thanks

     

    The Duke

  4. Hello

     

    I am new to the forum and not sure where to post - did read through - but still not 100% sure.

     

    My question relates to taking small claims action after insurance ombudsman has not found in my favour. I think I know what the process is but would be intersted in any view on likely success / court view is ombusman has already said no.

     

    Many thanks and happy to re post once I know where

     

    The Duke

×
×
  • Create New...