Jump to content


  • Tweets

  • Posts

    • Our price is the same all day, but varies day to day. Yes there's a risk of high prices but it has never gone above SVR any time since I signed up. Last 30 days average 17.67p/kWh, max 20.67 and lowest was 11.83.  It saved just under £300 during 2023.  
    • It you had E7 in the past but have converted to single rate then the meter will still hold the last recorded Night readings. This introduces scope for error when manually reading. If the meter has only ever been used on single rate then there's only one figure that can be taken. For example ours shows "Rate 1" reading and a "Total import" reading, but they both give the sme figure. If it has ever been on E7 the total will be higher, including the retained night reading.
    • okay, perfect and thank you so much for the help once again. so firstly i am going to initiate the breathing space, during this time it's likely ill receive a default. when i receive the default are you aware of how long it will take for me to know whether the OC have sold it off to DCAs? Once it's with the DCAs i do not need to worry as they cannot issue a CCJ only the OCs can Even if i decide to come an arrangement with the DCAs no point as the default will remain for 6 years paid or not paid I should only consider repayment if the OC still won the debt and then issue a CCJ? Just to confirm the default will not be seen after 6 years? No one can tell I had one then after 6 years ill be all good?
    • I'm not sure we were on standard tariffs - I've uploaded as many proofs as I can for the ombudsman - ovo called last night uping the compensation to 100 from 50 pounds for the slip in customer service however they won't acknowledge the the problem them not acknowledging a fault has caused nor are they willing to remedy anything as they won't accept the meter or formula was wrong.   I'd appreciate more details on the economy 7 approach and I'll update the ombudsman with any information you can share. 
    • To re-iterate and highlight my urgent question on this one: The N24 from the court did not include any instructions to submit paperwork 28 days before the date, unlike the N157 received for other smaller claims. Do I have to submit a WS for this court date? Link has!...
  • Recommended Topics

  • Our picks

    • If you are buying a used car – you need to read this survival guide.
        • Like
      • 1 reply
    • Hello,

      On 15/1/24 booked appointment with Big Motoring World (BMW) to view a mini on 17/1/24 at 8pm at their Enfield dealership.  

      Car was dirty and test drive was two circuits of roundabout on entry to the showroom.  Was p/x my car and rushed by sales exec and a manager into buying the mini and a 3yr warranty that night, sale all wrapped up by 10pm.  They strongly advised me taking warranty out on car that age (2017) and confirmed it was honoured at over 500 UK registered garages.

      The next day, 18/1/24 noticed amber engine warning light on dashboard , immediately phoned BMW aftercare team to ask for it to be investigated asap at nearest garage to me. After 15 mins on hold was told only their 5 service centres across the UK can deal with car issues with earliest date for inspection in March ! Said I’m not happy with that given what sales team advised or driving car. Told an amber warning light only advisory so to drive with caution and call back when light goes red.

      I’m not happy to do this, drive the car or with the after care experience (a sign of further stresses to come) so want a refund and to return the car asap.

      Please can you advise what I need to do today to get this done. 
       

      Many thanks 
      • 81 replies
    • Housing Association property flooding. https://www.consumeractiongroup.co.uk/topic/438641-housing-association-property-flooding/&do=findComment&comment=5124299
        • Like
      • 161 replies
    • We have finally managed to obtain the transcript of this case.

      The judge's reasoning is very useful and will certainly be helpful in any other cases relating to third-party rights where the customer has contracted with the courier company by using a broker.
      This is generally speaking the problem with using PackLink who are domiciled in Spain and very conveniently out of reach of the British justice system.

      Frankly I don't think that is any accident.

      One of the points that the judge made was that the customers contract with the broker specifically refers to the courier – and it is clear that the courier knows that they are acting for a third party. There is no need to name the third party. They just have to be recognisably part of a class of person – such as a sender or a recipient of the parcel.

      Please note that a recent case against UPS failed on exactly the same issue with the judge held that the Contracts (Rights of Third Parties) Act 1999 did not apply.

      We will be getting that transcript very soon. We will look at it and we will understand how the judge made such catastrophic mistakes. It was a very poor judgement.
      We will be recommending that people do include this adverse judgement in their bundle so that when they go to county court the judge will see both sides and see the arguments against this adverse judgement.
      Also, we will be to demonstrate to the judge that we are fair-minded and that we don't mind bringing everything to the attention of the judge even if it is against our own interests.
      This is good ethical practice.

      It would be very nice if the parcel delivery companies – including EVRi – practised this kind of thing as well.

       

      OT APPROVED, 365MC637, FAROOQ, EVRi, 12.07.23 (BRENT) - J v4.pdf
        • Like
  • Recommended Topics

Dunster House - Log Cabin Build Issue


style="text-align: center;">  

Thread Locked

because no one has posted on it for the last 2274 days.

If you need to add something to this thread then

 

Please click the "Report " link

 

at the bottom of one of the posts.

 

If you want to post a new story then

Please

Start your own new thread

That way you will attract more attention to your story and get more visitors and more help 

 

Thanks

Recommended Posts

I had the cabin components delivered on 8th January

 

Due to issues with the base we did not start building the cabin 25th January

 

We have now encountered a few issues with the build, and the company will only respond via e-mail and not over the phone which is dragging out the resolution of our queries

 

At the moment the doors will not align correctly and are out of alignment by 8mm.

We have now been told to put the glass into the doors as they will hang differently,

but we cannot see that this will resolve the situation

 

Now, we have found another problem in that all four panels of glass are scratched.

The company have asked for pictures but this is not easy to get as the scratches are hard to see even with black card behind them.

The company have advised that I signed for the goods at time of delivery as being in good condition, but there was no way you could check each item as there were hundreds of bits of wood as well as glass and plastic items.

 

I would like to ask for some advice on what to do next?

I paid by credit card so should I raise Section 75 for faulty goods if they won't replace the doors or glass

Edited by dx100uk
paras
Link to post
Share on other sites

the items are not fit for purpose/Faulty and you are within 30days

replace or refund FOC under CRA.

 

yes section 75 would apply too if they don't cough up

please don't hit Quote...just type we know what we said earlier..

DCA's view debtors as suckers, marks and mugs

NO DCA has ANY legal powers whatsoever on ANY debt no matter what it's Type

and they

are NOT and can NEVER  be BAILIFFS. even if a debt has been to court..

If everyone stopped blindly paying DCA's Tomorrow, their industry would collapse overnight... 

Link to post
Share on other sites

i cant comment on the getting replacement parts section of this

 

just be aware that we had a log cabin from gardenbuildingsdirect, this is the same sort of style that dunster sell

 

they can swell something horrible in wet weather, when its damp our door goes from fitting perfectly to having at least an inch to 2 inch gap at top and bottom, the window frames also swell slightly and will often push gaps into the wall

 

if its the same type of window then the plastic is just layed into the frame and then wooden trim nailed in around it to hold it into place, please remember to put some silicon seal around the edges of these, we have noticed that water has been running down the perspex and into the inside of the cabin through there, the wood is black on the window cross pieces after a year - even with treatment

 

same issue in the corner, we were given "trim" to be fitted to the inside of each corner, this didnt look or fit right so was left off, good job we did water also makes it through those corner gaps - again black after just a year, corners have now also had to be sealed with silicon - doesnt look right until its painted over but better than letting it rot

 

think next time i will simply build my own summer house - hope yours goes better than ours

Please note:

 

  • I am employed in the IT sector of a high street retail chain but am not posting in any official capacity,so therefore any comments,suggestions or opinions are expressly personal ones and should not be viewed as an endorsement or with agreement of any company.
  • i am not legal trained in any form.
  • I have many experiences in life and do often use these in my posts

if ive been helpful kick my scales, if ive been unhelpful kick the scales of the person more helpful :eek:

Link to post
Share on other sites

the items are not fit for purpose/Faulty and you are within 30days

replace or refund FOC under CRA.

 

yes section 75 would apply too if they don't cough up

 

Just a question on this. How does it stand when the building is partially erected and also the labour costs that the OP has incurred. I recommended the OP to come on here and know that they have had to pay labour costs where very little work has been done due to the problems. Could that be a consequential loss claim.